This project consisted of the removal and replacement of an old concrete radial gate diversion
structure with a new concrete diversion structure that incorporated an Obermeyer
Gate system. In addition, a new concrete radial gate structure was added to the existing canal structure to get the design flow rate of
800 cfs diverted into the canal. The project was designed in 1996.
Photographs Before Construction
 Existing radial gate canal structure |
 Existing diversion structure |
 Existing radial gate diversion structure |
 Existing radial gate diversion structure & canal structure |
 Existing ogee & diversion structure |
 Existing radial gate canal structure |
Photographs During Construction
 New diversion |
 New diversion |
 New diversion |
 New canal radial gate addition |
 New diversion |
 New diversion |
 New diversion |
 New canal radial gate addition |
 New canal radial gate addition |
Photographs After Construction
 New diversion in operation |
 Obermeyer gate system |
 New diversion in operation |
| |
|