Straw Bale Check Dam Fact Sheet
What is a Straw Bale Check Dam?These are temporary sediment barriers constructed of straw bales across very small drainages.
When is a Straw Bale Check Dam Used?
These temporary structures are used to slow debris flow. They are not
intended to provide protection from large storm events nor to control debris
flows in water bodies such as creeks, streams and rivers. Straw Bale Check Dam
design limits are as follows:
Straw Bale Check Dam Fact Sheet
Slope |
Maximum Drain Area Between Check Dams |
Maximum Slope Length |
0 -15 percent |
1 acre |
200 feet |
15 - 20 percent |
1/2 acre |
100 feet |
>20 percent |
Not Recommended |
|
How are Straw Bale Check Dams Installed?
Bales should be bound with wire or nylon string. Twine bound bales are less
durable. The bales should be placed in rows with bale ends tightly abutting the adjacent bales.
Downstream Row (refer to illustration): Dig a trench across
the small channel, wide enough and deep enough to so that the top of the row of
bales placed on their long, wide side is level with the ground. The tops of
bales across the center of the channel should all be level and set at the same
elevation. Place the bales in position and stake them according to the
instructions below.
Upstream Row: Dig another trench across the small channel,
upstream and immediately adjacent to the first row of bales. The trench should
be wide enough to accommodate a row of bales set vertically on their long edge.
The trench should be deep enough so that at least 6 inches of each bale is below
ground starting with the bale in the channel bottom. The trench should be as
level as possible so that the tops of the bales across the center of the channel
are level and water can flow evenly across them. Continue this trench up the
side slopes of the small channel to a point where the unburied bottom line of
the highest bale (point "C", illustration) is higher than the top of
the bales that are in the center of the channel (point "D",
illustration).
Anchorage: Drive 2 x 2 stakes or #4 rebar through the bales
and into the ground 1 1/2 to 2 feet for anchorage. The first stake in each bale
should be driven toward a previously laid bale to force the bales together (see
illustration).
Maintenance: Inspect the bale check dam and provide
necessary maintenance following each storm period. Remove the bales and stakes
once permanent drainage and stabilization is reestablished. Used straw can be
used as mulch in other areas.

NOTE: After a fire many trees are weakened from burning
around the base of the trunk. The trees can fall over or blow down
without warning. Shallow rooted trees can also fall. Therefore be
extremely alert when around burned trees. |